Flood Damage DRFA

Share Flood Damage DRFA on Facebook Share Flood Damage DRFA on Twitter Share Flood Damage DRFA on Linkedin Email Flood Damage DRFA link

Project Overview

The Disaster Recovery Funding Arrangements (DRFA) is a jointly funded program between the Australian Government, and State and Territory (states) Governments, through which the Australian Government provides financial assistance to support State Governments with disaster recovery costs.

Assistance has been activated for the following events which have been defined as:

  • Northern and Central Western Queensland Rainfall and Flooding event, 21 April – 12 May 2022 (2022 event)
  • Northern and Central Queensland Monsoon and Flooding, 20 December 2022 - 30 April 2023 (2023 event)
  • Tropical Cyclone Kirrily, associated rainfall and flooding, 25 January - 26 February 2024 (2024 event)
  • North and Far North Tropical Low, commencing 29 January 2025 (2025 event)
  • Western QLD Surface Trough and Associated Rainfall commencing 21 March 2025

Investment

Council has sought funding or is in the process of seeking funding for each of the above events to conduct Reconstruction of Essential Public Assets (REPA) within the Charters Towers region.

The projects are estimated to cost:

  • 2022 event - $5M
  • 2023 event - $60M
  • 2024 event - $45M
  • 2025 event - TBA

All submissions are subject to approval by the Queensland Reconstruction Authority (QRA).

Location

For the location of works please view the live map.

Contact Details

For further information relating to the project please phone Council on 07 4761 5300 or email mail@charterstowers.qld.gov.au

Project Status

ROAD PACKAGES - 2025 EVENT

Works Package (WP)StatusUpdate
WP01 Valley of Lagoons

Submissions lodged to QRA, pending approval. 4/4 approved.

Released for Request for Quote via Vendor Panel. Closes 23/01/2026.
Rolled over from 2024 Event due to substantial increase in damage from 2025 Event
WP02 Conjuboy

Submissions lodged to QRA, pending approval. 2/2 approved.

Preferred Contractor Nominated, contract negotiations underway.
Rolled over from 2024 Event due to substantial increase in damage from 2025 Event
WP03 Mount Fox

Submissions lodged to QRA, pending approval. 1/2 approved.

Released for Request for Quote via Vendor Panel. Closes 27/01/2026.
Rolled over from 2024 Event due to substantial increase in damage from 2025 Event
WP04 Jessie Springs

Submissions lodged to QRA, pending approval. 0/1 approved.

Work package is being contracted with WP08.
WP05 Hillgrove Niall

Submissions lodged to QRA, pending approval. 0/3 approved.

Released for Request for Quote via Vendor Panel. Closes 28/01/2026.
WP06 Ewan Laroona


Submissions lodged to QRA, pending approval. 0/2 approved.

Released for Request for Quote via Vendor Panel. Closes 29/01/2026.
WP07 Gregory Springs100 %

Scopes lodged to QRA on 14/03/2025. 1/1 submissions approved in MARS 04/08/2025.

Variation Approval on 16/09/2025, Mobilised 17/09/2025, Practical Completion 13/11/2024

Remaining Roads lodged to QRA on 11/12/2025. 0/3 submissions approved in MARS.

Remaining roads released for Request for Quote via Vendor Panel. Closes 05/02/2026.
WP08 Fletchervale

Submissions lodged to QRA, pending approval. 0/3 approved.

Released for Request for Quote via Vendor Panel. Closes 30/01/2026.
WP09 Dotswood

Submissions lodged to QRA, pending approval. 0/5 approved.

Released for Request for Quote via Vendor Panel. Closes 22/01/2026.
WP10 Myola

Submissions lodged to QRA, pending approval. 3/3 approved 09/12/2025.

Released for Request for Quote via Vendor Panel. Closes 21/01/2026.

WP11 Longton Yarrowmere39 %

Longton Road (CH. 2340-76050) – 57%

Longton Road (CH. 77460-12510) - 0%

Longton Road Bypass – 40%

Glen Houghton Road – 0%

WP12 Helenslee

Submissions lodged to QRA, pending approval. 4/6 approved.

Released for Request for Quote via Vendor Panel. Closes 16/01/2026.
Rolled over from 2024 Event due to substantial increase in damage from 2025 Event
WP13 Lornesleigh96%

Harvest Home Road – 96%

WP14 Burdekin Falls

Submissions lodged to QRA, pending approval. 0/1 approved.

Released for Request for Quote via Vendor Panel. Closes 03/02/2026.
WP15 Lake BuchananRoads are being assessed for damage and submission to QRA.

Submissions lodged to QRA, pending approval. 0/4 approved.

Released for Request for Quote via Vendor Panel. Closes 02/02/2026.
WP16 ScartwaterRolled over from 2024 Event due to substantial increase in damage from 2025 Event

Submissions lodged to QRA, pending approval. 5/5 approved.

Released for Request for Quote via Vendor Panel. Closes 20/01/2026.

WP17 Environs North


Submissions lodged to QRA, pending approval. 0/1 approved.

Tender Documents being prepared to release to the Contracting Market through CTRC’s Vendor Panel
WP18 Environs South
Submissions are being prepared for upload and lodgement to QRA

WP19 Broughton Crossing0%

Broughton Crossing – 0%

WP 20 Williams Crossing53%Laroona Road - 53%


ROAD PACKAGES - 2024 EVENT

Works Package (WP)StatusUpdate
WP01 Valley of Lagoons100%Due to the subsequent weather event, revised scopes have been lodged to QRA.
WP02 Conjuboy100%Due to the subsequent weather event, revised scopes have been lodged to QRA.
WP03 Mount Fox100%Due to the subsequent weather event, revised scopes have been lodged to QRA.
WP06 Ewan Laroona

53%

100%

Laroona Road (chainage 44,710, Williams Crossing) – works to be conducted in conjunction with WP19 Laroona Culvert.

Lassie Creek Road – 100% (completed as a variation to the 2023 scope of work)

WP07 Gregory Springs100%

Clarke Hills Road – 100%

Gregory Springs Road – 100%

Yering Road – 100%
WP11 Longton94 %

Binkar Road – 100%

Dump Road – 100%

Glen Houghton Road – 100%

Lauderdale Road – 100%

Longton Road (CH. 2340-76050) – 100%

Longton Road (CH. 77460-12510) - 100%

Longton Road Bypass – 100%

Narellan Road – 100%

Stockyard Creek Road – 100%

Stonington Road – 100%

Wantima Road – 29%

WP12 Helenslee100 %Due to the subsequent weather event, revised scopes have been lodged to QRA.
WP14 Burdekin Falls100 %

Construction works 100% physically complete.

MARS Acquittal Complete, pending QRA approvals.
WP15 Lake Buchanan100%

Due to the subsequent weather event, revised scopes have been lodged to QRA.

MARS Acquittal Complete, pending QRA approvals.

WP16 Scartwater47%

Scartwater Road – 100%

Bingeringo Road – 25%

Bulliwallah Road – 33%

Dandenong Road – 25%

Mount Hope Road – 100%

WP17 Environs North

Halloran & Son’s
100%

Construction works 100% physically complete

MARS Acquittal Complete, QRA final approvals received 19/09/2025.
WP19 Laroona Culvert73%

Laroona Culvert – 73%

WP20 Shrimp Battery68%

Shrimp Battery Road – 68%


ROAD PACKAGES - 2023 EVENT

Works Package (WP)StatusUpdate
WP01: Valley of Lagoons
Hammer & Co Earthmoving

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 23/09/2025.

WP02: Conjuboy
Hammer & Co Earthmoving

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 07/10/2025.

WP03: Mount Fox
Hammer & Co Earthmoving

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 23/09/2025.

WP04: Jessie Springs
WAR NQ

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 25/09/2025.

WP05: Hillgrove Niall
Mendi Group

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 26/07/2025.

WP06: Ewan Laroona
I&J Minns Haulage

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 16/10/2025.

WP07: Gregory Springs
I&J Minns Haulage

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 18/11/2025.

WP08: Fletchervale
Milray Contracting

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 07/10/2025.

WP09: Dotswood

Harcoo Enterprises

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 29/11/2025

WP10: Myola
Milray Contracting

100%


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 07/10/2025.

WP11: Longton Yarrowmere

NQ Civil & Haulage

100%

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 15/09/2025.

WP12: Helenslee
Halloran & Sons

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 15/09/2025.

WP13: Lornesleigh
Renick & Son’s

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, pending QRA final approvals.
WP14: Burdekin Falls
Hammer & Co Earthmoving

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 29/11/2025.
WP15: Lake Buchanan
Renick & Son’s

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 18/11/2025.
WP16: Scartwater
Milray Contracting

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 28/10/2025.
WP17: Environs North
Halloran & Sons

100 %

Construction works 100% physically complete

MARS Acquittal Complete, QRA final approvals received 15/09/2025.

WP18: Environs South
WAR NQ

100 %

Construction works 100% physically complete

MARS Acquittal Complete, QRA final approvals received 15/09/2025.



Project Overview

The Disaster Recovery Funding Arrangements (DRFA) is a jointly funded program between the Australian Government, and State and Territory (states) Governments, through which the Australian Government provides financial assistance to support State Governments with disaster recovery costs.

Assistance has been activated for the following events which have been defined as:

  • Northern and Central Western Queensland Rainfall and Flooding event, 21 April – 12 May 2022 (2022 event)
  • Northern and Central Queensland Monsoon and Flooding, 20 December 2022 - 30 April 2023 (2023 event)
  • Tropical Cyclone Kirrily, associated rainfall and flooding, 25 January - 26 February 2024 (2024 event)
  • North and Far North Tropical Low, commencing 29 January 2025 (2025 event)
  • Western QLD Surface Trough and Associated Rainfall commencing 21 March 2025

Investment

Council has sought funding or is in the process of seeking funding for each of the above events to conduct Reconstruction of Essential Public Assets (REPA) within the Charters Towers region.

The projects are estimated to cost:

  • 2022 event - $5M
  • 2023 event - $60M
  • 2024 event - $45M
  • 2025 event - TBA

All submissions are subject to approval by the Queensland Reconstruction Authority (QRA).

Location

For the location of works please view the live map.

Contact Details

For further information relating to the project please phone Council on 07 4761 5300 or email mail@charterstowers.qld.gov.au

Project Status

ROAD PACKAGES - 2025 EVENT

Works Package (WP)StatusUpdate
WP01 Valley of Lagoons

Submissions lodged to QRA, pending approval. 4/4 approved.

Released for Request for Quote via Vendor Panel. Closes 23/01/2026.
Rolled over from 2024 Event due to substantial increase in damage from 2025 Event
WP02 Conjuboy

Submissions lodged to QRA, pending approval. 2/2 approved.

Preferred Contractor Nominated, contract negotiations underway.
Rolled over from 2024 Event due to substantial increase in damage from 2025 Event
WP03 Mount Fox

Submissions lodged to QRA, pending approval. 1/2 approved.

Released for Request for Quote via Vendor Panel. Closes 27/01/2026.
Rolled over from 2024 Event due to substantial increase in damage from 2025 Event
WP04 Jessie Springs

Submissions lodged to QRA, pending approval. 0/1 approved.

Work package is being contracted with WP08.
WP05 Hillgrove Niall

Submissions lodged to QRA, pending approval. 0/3 approved.

Released for Request for Quote via Vendor Panel. Closes 28/01/2026.
WP06 Ewan Laroona


Submissions lodged to QRA, pending approval. 0/2 approved.

Released for Request for Quote via Vendor Panel. Closes 29/01/2026.
WP07 Gregory Springs100 %

Scopes lodged to QRA on 14/03/2025. 1/1 submissions approved in MARS 04/08/2025.

Variation Approval on 16/09/2025, Mobilised 17/09/2025, Practical Completion 13/11/2024

Remaining Roads lodged to QRA on 11/12/2025. 0/3 submissions approved in MARS.

Remaining roads released for Request for Quote via Vendor Panel. Closes 05/02/2026.
WP08 Fletchervale

Submissions lodged to QRA, pending approval. 0/3 approved.

Released for Request for Quote via Vendor Panel. Closes 30/01/2026.
WP09 Dotswood

Submissions lodged to QRA, pending approval. 0/5 approved.

Released for Request for Quote via Vendor Panel. Closes 22/01/2026.
WP10 Myola

Submissions lodged to QRA, pending approval. 3/3 approved 09/12/2025.

Released for Request for Quote via Vendor Panel. Closes 21/01/2026.

WP11 Longton Yarrowmere39 %

Longton Road (CH. 2340-76050) – 57%

Longton Road (CH. 77460-12510) - 0%

Longton Road Bypass – 40%

Glen Houghton Road – 0%

WP12 Helenslee

Submissions lodged to QRA, pending approval. 4/6 approved.

Released for Request for Quote via Vendor Panel. Closes 16/01/2026.
Rolled over from 2024 Event due to substantial increase in damage from 2025 Event
WP13 Lornesleigh96%

Harvest Home Road – 96%

WP14 Burdekin Falls

Submissions lodged to QRA, pending approval. 0/1 approved.

Released for Request for Quote via Vendor Panel. Closes 03/02/2026.
WP15 Lake BuchananRoads are being assessed for damage and submission to QRA.

Submissions lodged to QRA, pending approval. 0/4 approved.

Released for Request for Quote via Vendor Panel. Closes 02/02/2026.
WP16 ScartwaterRolled over from 2024 Event due to substantial increase in damage from 2025 Event

Submissions lodged to QRA, pending approval. 5/5 approved.

Released for Request for Quote via Vendor Panel. Closes 20/01/2026.

WP17 Environs North


Submissions lodged to QRA, pending approval. 0/1 approved.

Tender Documents being prepared to release to the Contracting Market through CTRC’s Vendor Panel
WP18 Environs South
Submissions are being prepared for upload and lodgement to QRA

WP19 Broughton Crossing0%

Broughton Crossing – 0%

WP 20 Williams Crossing53%Laroona Road - 53%


ROAD PACKAGES - 2024 EVENT

Works Package (WP)StatusUpdate
WP01 Valley of Lagoons100%Due to the subsequent weather event, revised scopes have been lodged to QRA.
WP02 Conjuboy100%Due to the subsequent weather event, revised scopes have been lodged to QRA.
WP03 Mount Fox100%Due to the subsequent weather event, revised scopes have been lodged to QRA.
WP06 Ewan Laroona

53%

100%

Laroona Road (chainage 44,710, Williams Crossing) – works to be conducted in conjunction with WP19 Laroona Culvert.

Lassie Creek Road – 100% (completed as a variation to the 2023 scope of work)

WP07 Gregory Springs100%

Clarke Hills Road – 100%

Gregory Springs Road – 100%

Yering Road – 100%
WP11 Longton94 %

Binkar Road – 100%

Dump Road – 100%

Glen Houghton Road – 100%

Lauderdale Road – 100%

Longton Road (CH. 2340-76050) – 100%

Longton Road (CH. 77460-12510) - 100%

Longton Road Bypass – 100%

Narellan Road – 100%

Stockyard Creek Road – 100%

Stonington Road – 100%

Wantima Road – 29%

WP12 Helenslee100 %Due to the subsequent weather event, revised scopes have been lodged to QRA.
WP14 Burdekin Falls100 %

Construction works 100% physically complete.

MARS Acquittal Complete, pending QRA approvals.
WP15 Lake Buchanan100%

Due to the subsequent weather event, revised scopes have been lodged to QRA.

MARS Acquittal Complete, pending QRA approvals.

WP16 Scartwater47%

Scartwater Road – 100%

Bingeringo Road – 25%

Bulliwallah Road – 33%

Dandenong Road – 25%

Mount Hope Road – 100%

WP17 Environs North

Halloran & Son’s
100%

Construction works 100% physically complete

MARS Acquittal Complete, QRA final approvals received 19/09/2025.
WP19 Laroona Culvert73%

Laroona Culvert – 73%

WP20 Shrimp Battery68%

Shrimp Battery Road – 68%


ROAD PACKAGES - 2023 EVENT

Works Package (WP)StatusUpdate
WP01: Valley of Lagoons
Hammer & Co Earthmoving

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 23/09/2025.

WP02: Conjuboy
Hammer & Co Earthmoving

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 07/10/2025.

WP03: Mount Fox
Hammer & Co Earthmoving

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 23/09/2025.

WP04: Jessie Springs
WAR NQ

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 25/09/2025.

WP05: Hillgrove Niall
Mendi Group

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 26/07/2025.

WP06: Ewan Laroona
I&J Minns Haulage

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 16/10/2025.

WP07: Gregory Springs
I&J Minns Haulage

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 18/11/2025.

WP08: Fletchervale
Milray Contracting

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 07/10/2025.

WP09: Dotswood

Harcoo Enterprises

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 29/11/2025

WP10: Myola
Milray Contracting

100%


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 07/10/2025.

WP11: Longton Yarrowmere

NQ Civil & Haulage

100%

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 15/09/2025.

WP12: Helenslee
Halloran & Sons

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 15/09/2025.

WP13: Lornesleigh
Renick & Son’s

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, pending QRA final approvals.
WP14: Burdekin Falls
Hammer & Co Earthmoving

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 29/11/2025.
WP15: Lake Buchanan
Renick & Son’s

100 %

Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 18/11/2025.
WP16: Scartwater
Milray Contracting

100 %


Construction works 100% physically complete.

MARS Acquittal Complete, QRA final approvals received 28/10/2025.
WP17: Environs North
Halloran & Sons

100 %

Construction works 100% physically complete

MARS Acquittal Complete, QRA final approvals received 15/09/2025.

WP18: Environs South
WAR NQ

100 %

Construction works 100% physically complete

MARS Acquittal Complete, QRA final approvals received 15/09/2025.



Page last updated: 16 Dec 2025, 03:16 PM